Portfolio
Projects are located in high solar PV potential regions
Projects are located in high solar PV potential regions connected to the national grid taking advantage of transmission lines and a proximity to consumption sources.
Assets will be producing energy at a constant price throughout the course of the next 14 years under the PMGD regulation which will no longer be available for new projects due to the implementation of block of hours price policy.
Projects
Catemu
Legal Entity: Parque Solar Catemu SpA
Location: Quillota
Operational Status: Operational
Capacity: 2.42 MW
Bicentenario
Legal Entity: Fotovoltaica Laurel SpA
Location: Charrúa
Operational Status: Operational
Capacity: 2.99 MW
El Cuervo
Legal Entity: PFV El Cuervo SpA
Location: Itahue
Operational Status: Mechanical Completion
Capacity: 2.99 MW
Faramalla
Legal Entity: Parque Fotovoltaico Faramalla SpA
Location: Melipilla
Operational Status: Mechanical Completion
Capacity: 3.00 MW
Encino
Legal Entity: Energía Renovable Encino SpA
Location: Alto Jahuel
Operational Status: Under Construction
Capacity: 2.99 MW
La Alcaldesa
Legal Entity: Parque Solar Alcaldesa SpA
Location: Charrúa
Operational Status: Operational
Capacity: 7.15 MW
Fardela Negra
Legal Entity: Fardela Negra SpA
Location: San Geronimo
Operational Status: Mechanical Completion
Capacity: 2.99 MW
Curicura
Legal Entity: Parque Solar Aurora SpA
Location: Itahue
Operational Status: Mechanical Completion
Capacity: 10.97 MW
Tórtola
Legal Entity: Tórtola SpA
Location: Quillota
Operational Status: Under Construction
Capacity: 2.99 MW
La Muralla
Legal Entity: Parque Solar La Muralla SpA
Location: Itahue
Operational Status: Operational
Capacity: 2.99 MW
Pencahue Este
Legal Entity: Parque Solar Porvenir SpA
Location: Ancoa
Operational Status: Operational
Capacity: 2.99 MW
Aeropuerto
Legal Entity: Parque Solar Retiro SpA
Location: Ancoa
Operational Status: Mechanical Completion
Capacity: 5.94 MW
7 Colores
Legal Entity: Siete Colores SpA
Location: Los Vilos
Operational Status: Under Construction
Capacity: 10.50 MW
Ciprés
Legal Entity: Empresa Eléctrica Ciprés SpA
Location: Charrúa
Operational Status: Under Construction
Capacity: 10.50 MW
Guindo Santo
Legal Entity: Empresa Eléctrica Guindo Santo SpA
Location: Charrúa
Operational Status: Under Construction
Capacity: 10.50 MW
Raulí
Legal Entity: Empresa Eléctrica Raulí SpA
Location: Charrúa
Operational Status: Under Construction
Capacity: 10.50 MW
San Marino
Legal Entity: San Marino Solar SpA
Location: Los Vilos
Operational Status: Under Construction
Capacity: 10.13 MW
Cefalú
Legal Entity: Cefalú Solar SpA
Location: Las Arañas
Operational Status: Under Construction
Capacity: 2.99 MW
Pesaro
Legal Entity: Pesaro Solar SpA
Location: San Antonio
Operational Status: Under Construction
Capacity: 2.99 MW